PJM wants an earlier answer for data centers, and fewer surprises once they draw power
Two PJM filings address different moments in a data center’s life: when it learns the cost of connecting and what the grid needs once it draws power.
Published November 21, 2026Intelligence / Energy / Grid Technology

A utility that knows a large customer can cut demand at an agreed time has something valuable to plan around. A grid operator that suddenly loses the same customer’s demand has a different problem. Power plants are still producing for a load that has vanished. For a brief interval, the grid has too much supply.
PJM, the regional grid operator serving much of the Mid-Atlantic and parts of the Midwest, encountered that second problem on July 22. It reports that roughly 3.9 gigawatts of demand transferred off the grid in one event. Frequency across the Eastern Interconnection reached 60.092 hertz, above its usual 60, and PJM reports a peak voltage of about 1.138 times nominal. The gigawatts describe the change in electricity drawn from the system. They say nothing about how much backup generation the customers owned.
That experience helps explain two proposals PJM filed separately with federal regulators on November 16. One would study new power plants and requests to supply large customers together, cutting the projected study period from about two years to one. The other would require customers taking transmission service for qualifying computing facilities to arrange for them to stay connected through specified brief grid disturbances. One proposal asks how soon planners can give a project a useful answer. The other asks what operators can count on after the customer arrives.
The Federal Energy Regulatory Commission’s June orders, covered here on November 3, asked operators to justify or change their treatment of large loads. PJM has now specified how an applicant could get earlier cost information, when it would have to commit money and which facilities would face the proposed operating rules. Both filings were proposals as of November 20.
What a year of study would buy
Under PJM’s Fast Energization proposal, planners would study proposed generation alongside eligible transmission-service requests for new demand. This gives them a chance to calculate the combined effects on the same lines and substations. During an approximately four-month screening phase, applicants would get two rounds of preliminary estimates for upgrade costs and construction times. A developer could withdraw before committing more money to a location where the upgrades make its project uneconomic.
The proposed tariff puts a price on entering that process. It specifies a nonrefundable $20,000 early-engagement deposit and a second nonrefundable study deposit scaled to the size of the request. For a 100-megawatt request, the second payment would be $250,000. These payments purchase study work. A project that needs a new substation or transmission line still has to secure, build and commission it. A twelve-month study clock promises no particular date for turning on servers.
PJM projects the first application window for the new cycle would open in late November 2027. It requested March 16, 2027, for specified tariff and transmission-service provisions and left the effective date of other changes open. Among the proposed service choices are interim network service and firm or non-firm service for a contracted amount of demand. Under the proposal, PJM could curtail interim or non-firm contract service during capacity or reserve shortages. A customer choosing those terms would know in advance that access to the grid could be limited.
Why a planned reduction differs from a sudden transfer
During an unexpected transfer, customers may continue computing on backup power while their draw on the regional system drops. From inside a building, continuity can look like success. From the grid control room, simultaneous transfers can magnify the disturbance that prompted them. PJM cites smaller events in 2024 and 2025 as well as July’s. The November development is its proposed response to that operating history.
The separate ride-through filing concerns a subset of customers. PJM starts with the existing large-load definition, at least 50 megawatts of cumulative peak demand at one electrical site. The proposed computing category requires at least 25 megawatts of maximum load served through power-electronic conversion equipment within that large load. The obligation would fall on the eligible customer taking transmission service on the facility’s behalf. The proposal reaches new and materially modified facilities and gives qualifying transitional facilities more time to comply. PJM requested January 16, 2027, for this filing; detailed operating requirements would be set out in its manuals.
A faster study can tell a town, utility and developer earlier what a campus will require and what the upgrades might cost. The operating proposal addresses a question nobody can settle with a construction estimate: whether the load planners studied will behave as expected when the grid is under stress. Regulators can evaluate the merits of each proposal separately. The useful evidence, if they take effect, will be how early applicants receive credible upgrade estimates and whether the system sees fewer large, unplanned transfers.
Sources
PJM Fast Energization filing, ER27-531 · PJM ride-through filing, ER27-522, including the July measurements · PJM’s explanation of the projected study timetable · November 3 coverage of FERC’s June orders
Sources · 4
- https://www.pjm.com/-/media/DotCom/documents/ferc/filings/2026/20261116-er27-531-000.pdf
- https://www.pjm.com/-/media/DotCom/documents/ferc/filings/2026/20261116-er27-522-000.pdf
- https://insidelines.pjm.com/pjm-proposal-would-cut-interconnection-process-time-in-half/
- https://www.jetsonsage.com/analysis/data-center-gas-plans-power-sector-emissions