Before a lender can put a value on a data center that will take years to build, it has to answer an uncomfortable question. Who would want the building if its first tenant stopped paying? In Pike County, Ohio, one answer is the company that hopes to supply the computers inside.

Nvidia has offered a backstop on the first nine buildings planned for SB Energy’s PORTS-Pike Technology Campus, on the former federal Portsmouth site. An OpenAI affiliate has signed the leases. If a covered building enters service and its tenant later defaults in specified circumstances, Nvidia can take over the tenancy, find an assignee or have the landlord seek another occupant. Together the agreements carry a $105 billion ceiling. On November 17, Nvidia reported that it had made no payments under its guarantees. Nvidia CFO commentary · SB Energy amended prospectus, pp. 193–194 and 210

The deal dates to August. What SB Energy’s November 19 filing makes easier to see is how a promise payable much later can influence a decision today. A lender considering a construction loan can give some credit to the value of a completed building even if the original tenant fails. The supplier gains something valuable in return. For 20 years, subject to limited exceptions, the covered premises are reserved for computing infrastructure built to Nvidia’s architecture. August disclosure · Building 1 guaranty

That makes Ohio a particularly good place to investigate a recurring suspicion about the AI boom: suppliers may be helping create the demand they cite as evidence of growth. The contract establishes the first half of that argument. Nvidia is helping make a customer’s premises financeable. The second half turns on who eventually pays for the computing done there. A guaranty can make a building easier to finance without bringing a single paying user through its doors.

Before the first rent payment

SB Energy counted the Ohio campus as contracted and outside its under-construction portfolio in the November filing. The developer signed 17 individual leases, each for a building designed for roughly 472 megawatts of critical computing load. Nine buildings account for about 4.25 gigawatts. Nvidia has the option to support another 3.78 gigawatts at its discretion. If it declines by the contractual deadline, OpenAI must secure a replacement guarantor meeting the specified credit standard. The $105 billion cap covers the initial nine. SB Energy, Business and Customer Contracts

Rent starts in phases when the relevant conditions are met. They include commissioned premises and the interconnection and generating resources needed to serve the load. The developer expected lease commencements between 2028 and 2032. Nvidia expected its first guaranty to take effect in its fiscal 2029, as the related building becomes ready for service. A delay in permits, financing or power can postpone that point. The lease gives the tenant remedies for certain missed milestones. A prospective lender still has construction and delivery risk to price before Nvidia’s support becomes effective. SB Energy, pp. 209–211 and 252–253 · Nvidia CFO commentary

What happens if one building loses its tenant?

Suppose one covered building has entered service and its tenant misses a payment, then fails to cure the default. This is a hypothetical. The guaranty identifies a qualifying monetary default or specified tenant insolvency as the trigger. A slow month for AI subscriptions would have no such effect by itself. OpenAI separately compensates Nvidia for the backstop. SB Energy says it owes Nvidia no fee for providing it. SB Energy, p. 210

Nvidia could take the tenancy and put the building to work, or assign it to someone else. It could also direct SB Energy to re-let the premises and, if that fails, sell them. The outside tenant’s willingness to pay would then become unusually informative. Another operator willing to take the building on comparable terms would preserve much of its economic value. A specialized shell with few bidders could leave a much larger covered loss. The scheduled minimum value declines over the lease and is designed to cover items including debt principal, interest, invested equity, targeted equity returns and committed transmission payments. The public exhibit redacts parts of the calculation. A precise payout for this imagined building cannot be derived from the headline cap. Building 1 agreement and schedules · SB Energy, p. 210

Nvidia can defer its choice for up to a year under specified terms. SB Energy expects the tenant’s deposit and project reserves to fund specified costs in the first six months after the trigger. Qualifying support can also end Nvidia’s role altogether, including a designated OpenAI parent credit rating or an eligible replacement guaranty or lease. A building could thus owe part of its initial financing appeal to Nvidia and ultimately operate for years without that support. SB Energy, Customer Contracts

The power bill has its own chain of promises

AEP Ohio and its affiliates expect roughly $5.1 billion of regional grid investment to serve the campus, according to SB Energy. Under the proposed arrangement the utility would recover capital costs, a regulated return and certain other expenses through charges to SB Energy. The developer expects to post collateral and to pass operating costs through to OpenAI during the leases. Those are proposed protections for other customers. The filing identifies no $5.1 billion charge already borne by households. SB Energy, pp. 193–194

The first 0.8 gigawatt of load has a utility service agreement conditional on transmission upgrades. Agreements for the larger transmission expansion and cost allocation were at different stages and subject to final approvals. Retail energy and capacity supply arrangements remained unfinished. A lender can value Nvidia’s promise and still conclude that a particular building will wait for power. For the households outside the campus, the consequential documents will be the executed utility terms, collateral requirements and regulatory allocation of costs if the buildout falls short. SB Energy, p. 211

Who finally buys the computing time?

CoreWeave offers a comparison with an observable difference. Nvidia bought $2 billion of its Class A shares. Under a separate order with an initial value of $6.3 billion, Nvidia has access to residual cloud capacity unsold to other customers, subject to the agreement’s terms. Equity gives Nvidia a stake in the company. Buying residual capacity can give it computing time. In Ohio, its backstop supports the value of leased premises after a specified trigger. These instruments answer different questions about demand, and adding their face values would answer none of them. CoreWeave equity disclosure · CoreWeave capacity order

The clearest evidence of independent demand in Ohio would come in sequence. Buildings enter service, rent arrives, and customers outside the financing arrangements repeatedly pay enough for computing to sustain that rent. A qualified third party replacing Nvidia’s support on commercial terms would be another indication that someone else is willing to carry the risk. Conversely, repeated extensions, dependence on new vendor support to fill completed halls, or a large discount to attract a replacement tenant would strengthen the case that the supplier had underwritten more demand than the market could support on its own. Even then, construction delays and weak end demand would need separate explanations.

For now, the chipmaker has done something consequential without writing a $105 billion check. It has given lenders a reason to consider what nine completed buildings might be worth to Nvidia itself. What those buildings will be worth to everyone else is a question the first lease signature could never settle.

Sources · 2