A data center in one state can change the air in another

An MIT study traced how electricity demand changes which generators run and where people breathe the resulting pollution.

Published November 20, 2026Analysis / Energy / Grid Technology

A county considering a data center can map the proposed building, its substation and the homes nearest its backup generators. The people whose air changes when its servers draw electricity may live outside every boundary on that map. A November study led by MIT found that some of the largest estimated health burdens per person from U.S. data-center electricity use fell in Midwestern states, including places far from the largest concentrations of servers. There are two journeys involved. Electricity can reach a customer from a distant generator. Pollution from that generator sets off downwind on a journey of its own.

For 2023, Lawrence Berkeley National Laboratory estimated that U.S. data centers used 176 terawatt-hours, or 4.4 percent of national electricity consumption. To trace the air-quality effects, Yuang (Albert) Chen and colleagues asked which power plants would have generated less electricity if the grid had served the rest of its customers that year without the data-center load. It sounds like a question for a meter reader. Even a perfectly accurate meter at the substation would record only the world in which the data center existed.

Reconstructing the hour that never happened

The researchers ran an electricity-generation model twice. They represented data centers as a steady load around the clock. In one run the grid served them. In the other that demand disappeared. A generator already producing at its limit might supply a large share of a region’s annual electricity and barely change output between the two runs. A plant with room to increase production might account for much of the difference in a particular hour. Transmission capacity affects which of the available plants can respond. An extra megawatt in Virginia can change generation in the Ohio Valley.

Having located the change in generation, the team estimated each plant’s change in emissions. Coal combustion can release sulfur dioxide. Fossil-fuel combustion also produces nitrogen oxides. The researchers fed the emissions into GEOS-Chem, a model of atmospheric transport and chemistry. In farm country, ammonia already in the air can help convert products of those emissions into fine particles. A population can therefore bear a substantial burden through the combination of an upwind power plant and its own atmospheric chemistry. Counting server halls in that population’s county would miss both.

Ozone provides a particularly revealing check on the idea that one extra megawatt has one fixed health cost. In the simulations, additional emissions could reduce ozone in winter and increase it in summer. The reactions depend on the chemical mixture and season. A smokestack inventory gives the location and amount of a release. Reaching a health estimate also requires knowing what forms in the air and who lives where it goes.

The team applied published exposure–response relationships to the modeled change in pollution across the contiguous United States. Fine particles accounted for an estimated 513 premature deaths in 2023, with a 95 percent interval of 469 to 557. For ozone the estimate was 137, with an interval of 90 to 183. Together the central estimates come to about 650. These are population-level estimates of a change in risk across two simulated worlds. There is no list of 650 identified people, and the two intervals cannot simply be added to produce a national confidence interval. The calculation concerns grid electricity for data centers broadly. Assigning it to AI alone would require knowing which equipment was doing which work.

What a clean-power contract leaves open

A developer might offer to move a batch of computation from an evening hour into a sunny afternoon. If solar output would otherwise have been curtailed in that place and hour, the move could spare a fossil generator some work. If all the available solar was already serving customers and a gas plant supplied the extra load, the same schedule change would produce a different result. Buying a year’s worth of renewable energy to match annual consumption leaves that physical question open. A new renewable project that changes actual dispatch deserves credit for the change it causes. The contract total alone cannot locate the plume.

A separate research team looked at 403 U.S. hyperscale facilities from May 2024 through April 2025. Its central estimates were about 82 terawatt-hours of consumption and 25.7 million metric tons of attributed carbon dioxide. Those totals imply roughly 313 grams of CO₂ per kilowatt-hour across that sample. They describe regional electricity attribution for a narrower population in a later period. A planner cannot multiply that carbon intensity by a proposed campus’s load to recover the MIT mortality calculation. Carbon dioxide accumulates globally. Fine-particle exposure depends on the responding generator, the weather, the chemistry and the population downwind.

For a proposed site, the most consequential missing document may be an hourly operating schedule. A useful permit analysis would test that schedule against alternative sites or operating hours, including the hour when deferred work resumes. It would separate grid power from fuel burned on the premises and test whether transmission limits or future plant retirements change which generators respond. The MIT study reconstructs a year on an existing grid. A campus large enough to prompt construction of a power plant poses a different question about years of future operation. A community assessing that prospect has good reason to invite its downwind neighbors into the discussion, however distant the nearest server may be.

Sources. Chen et al., study abstract and estimates · MIT interviews and model description · Berkeley Lab national electricity estimate · Guidi et al., hyperscale study · Authors’ versioned aggregate data · EPA’s independent marginal-emissions modeling framework.